Project Description

Construction of Asphaltic Highway, Highway No.12 Tak – Amphur Mae Sort Route, Section 3 Part 2

From Km.61+791.902 (Highway No.12) – Km. 73+891.138 (Highway No.12) Approximate distance: 12.100 Km.

Details

Contract no.
สท.1/24/2558

Date signed

June 10th, 2015

Commencement date

June 11th, 2015

Contract ends

January 17th, 2017

Completion date

January 16th, 2017

Time for completion

935 days

Construction value

THB 650,794,071.30

Bank guarantee document by Kasikorn Bank PCL ,Tiwanon (Khaerai) Branch

No.58-42-3081-9, signed on June 2nd, 2015 Amount: THB 34,525,000.00

Project owner

Department of Highways