Project Description
Construction of Asphaltic Highway, Highway No.12 Tak – Amphur Mae Sort Route, Section 3 Part 1
from Km.49+266.137 (Highway No.12) – Km. 61+791.902 (Highway No.12) Approximate distance: 12.525 Km.
Details
Contract no.
สท.1/23/2558
Date signed
June 10th, 2015
Commencement date
June 11th, 2015
Contract ends
February 16th, 2018
Completion date
February 15th, 2018
Time for completion
964 days
Construction value
THB 681,045,539.91
Bank guarantee document by Krungthai Bank PCL, Phahonyothin 39 Branch
No.00019/200142/0003/58, signed on June 2nd, 2015 Amount: THB 35,300,000.00
Project owner
Department of Highways