Project Description

Project: Highway no. 12: Sukhothai – Tak Part 2

From Km.63+500.000 – Km. 90+000.000 Approximate distance: 26.500 Km.

Details

Contract no.
สท.1/1/2550

Date signed

December 22nd, 2006

Commencement date

December 23rd, 2006

Contract ends

August 13th, 2008

Completion date

July 31st, 2008

Time for completion

818 days

Construction value

THB 474,781,771.00

Bank guarantee document by TMB Bank PCL , Sukhothai Branch

No. 2100000077/2006, signed on December 18th, 2006 Amount: THB 24,089,089.00

Project owner

Department of Highways