Project Description

Project: Highway No.36 : Kratinglai-Rayong route (Including Crossing Rayong Section 3, Thap Ma Intersection and Ban Don Intersection), Nong Bon-Ban Laeng Intersection, Section 1

From Km.33+000.000 – Km.45+000.000 Approximate distance: 12 Km.

Details

Contract no.

สท.1/29/2561

Date signed

February 26, 2018

Commencement date

February 27, 2018

Contract ends

April 4, 2021

Completion date

April 3, 2021

Time for completion

900 days

Construction value

THB 1,024,632,000

Bank guarantee document by Krungthai Bank PCL, Phahonyothin 39 Branch

No.00019/200142/0001/61, signed on February 20, 2018 Amount: THB 51,231,600.00

Project owner

Department of Highways