Project Description

Landscape decoration project for the promotion of tourism, Wat Phra Si Mahathat, Phitsanulok

Details

Contract no.
66/2562

Date signed

February 14th, 2019

Commencement date

February 15th, 2019

Contract ends

March 15th, 2020

Completion date

March 15th, 2020

Time for completion

390 days

Construction value

THB 37,111,632.95

Bank guarantee document by Kasikorn Bank PCL ,Tiwanon (Khaerai) Branch

No.100022794005, signed on February 14th, 2019 Amount: THB 1,883,600.00

Project owner

Phitsanulok Municipality