Project Description
Construction of Asphaltic Highway, Highway No.12 Tak – Amphur Mae Sort Route, Section 3 Part 2
From Km.61+791.902 (Highway No.12) – Km. 73+891.138 (Highway No.12) Approximate distance: 12.100 Km.
Details
Contract no.
สท.1/24/2558
Date signed
June 10th, 2015
Commencement date
June 11th, 2015
Contract ends
January 17th, 2017
Completion date
January 16th, 2017
Time for completion
935 days
Construction value
THB 650,794,071.30
Bank guarantee document by Kasikorn Bank PCL ,Tiwanon (Khaerai) Branch
No.58-42-3081-9, signed on June 2nd, 2015 Amount: THB 34,525,000.00
Project owner
Department of Highways