Project Description
Project: Highway no. 12: Sukhothai – Tak Part 3
From Km.90+000.000 – Km. 112+905.504 Approximate distance: 22.905 Km.
Details
Contract no.
สท.1/11/2553
Date signed
August 10th, 2010
Commencement date
August 10th, 2010
Contract ends
December 7th, 2013
Completion date
November 22nd, 2013
Time for completion
1,181 days
Construction value
THB 607,202,032.09
Bank guarantee document by Kasikorn Bank PCL ,Tiwanon (Khaerai)Branch
No. 53-42-2436-1, signed on August 10th, 2010 Amount: THB 30,597,587.00
Project owner
Department of Highways