Project Description
Construction of Asphaltic Highway, Highway No.126 – Southern Phisanulok Bypass, Part 1
From Km.29+203.000 – Km. 42+150.000 Approximate distance: 12.947 Km.
Details
Contract no.
สท.1/8/2556
Date signed
August 9th, 2013
Commencement date
August 10th, 2013
Contract ends
September 9th, 2015
Completion date
September 4th, 2015
Time for completion
744 days
Construction value
THB 598,243,495.86
Bank guarantee document by Kasikorn Bank PCL ,Tiwanon (Khaerai) Branch
No.56-42-3487-9, signed on July 24th, 2013 Amount: THB 29,933,338.00
Project owner
Department of Highways