Project Description

Nong Tung Lan Chang Kaem Ling water resource restoration project Tanot, Khiri Mat, Sukhothai

Project No: สท.08-04-045/2 

Details

Contract no.
สทภ.9 125/2555

Date signed

July 5th, 2012

Commencement date

July 6th, 2012

Contract ends

June 8th, 2013

Completion date

February 14th, 2013

Time for completion

218 days

Construction value

THB 23,232,323.00

Bank guarantee document by Kasikorn Bank PCL ,Tiwanon (Khaerai) Branch

No.55-42-3058-8 , signed on July 2nd, 2012 Amount: THB 1,161,616.15

Project owner

Water Resources Regional Office 9